Area: 710 hectares
Development of internal access road network: 2x1 lane road ~7,000 m, 2x2 lane road: ~9,000 m
Construction of roundabout junctions within the zone: 2
Development of pedestrian and bicycle infrastructure: ~18,400 m
Development of drinking water utility: ~18,800 m
Development of communal wastewater utility: ~12,500 m
Development of industrial wastewater utility: ~ 9,255 m
Development of industrial water (“grey water”) utility ~1,200 m
Development of electricity network: new 400/132 kV transmission station, new 132kV substation
Solar park development: 41 hectares
Gas network development: ~26,400 m
Communications substructure development: 19,500 m
Groundwater and stormwater drainage system development: 13,300 m
Extension of stormwater reservoir capacities: on an area of ~ 75 hectares